VANTOR FLOORING / STRATA PROJECT CASE STUDY
15 floors of strata carpet replaced in just four weekdays
9,000 sq. ft. of aging broadloom replaced with commercial carpet tile across 15 floors of an occupied Vancouver condominium—completed over four weekdays with resident-conscious scheduling.
Project highlights
Building type
Occupied Vancouver strata condominium
Flooring
Commercial carpet tile replacing broadloom
Scope
Broadloom removal, adhesive removal, disposal, floor preparation and carpet tile installation






Completed Chinatown strata carpet tile replacement — swipe or scroll for more photos
Swipe or scroll horizontally to view more project photos.
01 / THE BRIEF
Renewing 15 floors of flooring in an occupied condominium
An aging broadloom carpet installation across 15 floors of a Chinatown strata building needed replacement. The project covered approximately 9,000 square feet of common-area flooring. The objective was to refresh the building's corridors while choosing a carpet system that would be easier to maintain and repair.
Carpet tile offered a practical alternative to broadloom. Individual tiles can be selectively replaced after staining, localized damage or water-related maintenance, potentially avoiding the need to replace large continuous sections of carpet.
02 / THE CHALLENGE
Residents at home. Four weekdays to complete 15 floors.
The condominium remained occupied throughout the replacement, with residents needing access to their suites and shared corridors. Work included lifting worn broadloom, collecting and disposing of waste, mechanically removing residual adhesive with a floor buffer, and preparing surfaces for carpet tile. The schedule also needed to limit residents' exposure to active work areas and flooring adhesive.


To meet the four-day schedule, each day's removal and preparation had to stay ahead of installation. Coordinating two crews, floor-by-floor sequencing, waste handling and end-of-day housekeeping was central to keeping the building usable.
03 / THE EXECUTION
Two synchronized crews, working ahead floor by floor
Divide the work
One crew removed the existing broadloom, managed disposal and prepared the substrate while a second crew followed behind to install new carpet tile.
Prepare floors ahead
At the end of each shift, the removal crew aimed to leave two or three additional floors prepared, allowing installers to start immediately the next morning.
Install the carpet tile
Install approximately 9,000 square feet of carpet tile through the building's common-area corridors as prepared floors became available.
Finish before evening
End weekday shifts before many residents returned from work, with daily housekeeping and attention to occupied-building access and adhesive exposure.




04 / THE RESULT
15 floors completed in four weekdays
Vantor Flooring completed broadloom removal, disposal, mechanical adhesive preparation and new carpet tile installation across approximately 9,000 square feet and 15 floors in four weekdays. The condominium remained occupied while the crew worked through a coordinated sequence of removal and installation. The refreshed common areas now have carpet tile flooring designed to simplify localized maintenance and future repairs.
Completed strata flooring gallery
A closer look at the completed carpet tile installation in condominium corridors, outside suite entrances and at elevator lobbies.










Planning a strata flooring replacement?
Vantor Flooring coordinates carpet replacement, floor preparation and carpet tile installation in occupied strata buildings throughout Metro Vancouver, with scheduling designed to reduce disruption for residents.